|
CMHS Construction Updates
Building a New Community Memorial Hospital
Modernizing Ojai Valley Community Hospital
July 2010 CMHS Project Bulletin

GARY K. WILDE
President & CEO,
Community Memorial Health System
We hope that you find this building update
informative. Our goal is to keep you informed
throughout the entire process with
these periodic updates.

Many key components to the infrastructure
of the new Cancer Center were completed
during the months of May and June. Workers
finished the final phase of the structural steel
framing of the two-story building. While
that was occurring, visitors
may have noticed a sharp contrast
to the building: distinct
wood framing in the northeast
corner of the site.
That wood framing, construction
officials explained, was
the formation of the walls for
the radiation vault. Once all
the concrete was poured, the
wood framing was removed.
The radiation vaults – with
some walls as thick as 8 feet
– took nearly 600 yards of
concrete and roughly 20 days
to complete. In the beginning
of June, an additional five
days were needed for workers
to pour the ceiling and complete
the vaults.
The corrugated metal roof decking was
completed and the concrete floors between
the first and second levels were poured.
Construction teams from a variety of trades
then began work on the interior mechanical
systems including plumbing, electrical, duct
work, and the fire sprinkler systems which
will continue through July.
The month will also see crews installing
interior drywall, as well as roofing and
waterproofing the exterior. Work will then
begin on installing the window frames and
storefront glass. Additionally, site grading
and paving will begin on the center’s parking
lot.
Construction officials report that the project
is moving along as scheduled, and the
structure really began to take shape once
the exterior framework began in June.

In our last Project Bulletin, we reported that
the Environmental Impact Review had been
distributed for public and agency comments.
We did receive some remarks to the
45-page document that have been received
by the City of Ventura, and their staff is now
addressing those comments.
We are also working closely with the City to
reach the final stages of the street improvements
and property exchanges. We are still
on track with these elements and expect that
this phase will be finalized and approved by
mid July.
While we are working with the city, we
continue to move through the permit
process with the California Office of State
Health Planning and Development and
anticipate receiving final state approval by
late fall. Although there is much going on
‘behind the scenes,’ neighbors and visitors
will soon see the demolition of several
homes and buildings to the southwest of
CMH. Demolition of those structures in the
area known as the “triangle” – the parcel
of land that encompasses Brent, Cabrillo
and Glen streets – will begin around July
15th, and should be completed by the end
of the month.
Additionally, site preparation will begin in the
fall in the alley way adjacent to the hospital’s
loading dock. This first phase will begin with
relocating the utilities and will not result in
any power interruptions for our neighbors.
As a reminder during this time the hospital
continues to offer hospital visitors valet
parking - free of charge - in the four-story
parking structure located near the CMH
Emergency Department.

The new 250kW generator was installed,
tested, and is up and running. This state-ofthe-
art generator with automatic transfer
switches replaces the three older models at
the hospital.
Located at the back the facility, the generator
will handle all of the electrical needs for
the hospital and the Continuing Care Center
in the case of a power outage. Moreover,
the high-tech machine’s life span reaches to
2055, and has additional capacity for growth.
This installation completes the first phase
of the OVCH remodel and work is now well
underway on the second stage – converting
the old emergency room into the PACU (Post
Anesthesia Care Unit).
To help control construction costs and to
get the unit ready for the general contractor,
staff at the facility has done preliminary work
including the demolition of various walls and
flooring, and the removal of outdated electrical
and plumbing systems.
As indicated in our last Project Bulletin, we
originally thought the PACU would be done
by mid July. Due to unforeseen electrical and
plumbing issues, and added scope of work
it is now scheduled to be done by fall. Once
completed, the PACU will feature 600 square
feet of space and will be a centrally located
recovery unit adjacent to the hospital’s two
operating rooms.
Moreover, when the PACU is finished, work
will then begin outside of the hospital repaving
the entire facility. It was determined the
paving should take place only when the
PACU construction vehicles are off site. This
will be done in stages and is projected to
take until the end of the year to complete.


Gary K. Wilde, President & CEO
Community Memorial Health System
|