|
CMHS Construction Updates
Building a New Community Memorial Hospital
Modernizing Ojai Valley Community Hospital
November 2010 CMHS Project Bulletin

GARY K. WILDE
President & CEO,
Community Memorial Health System
This installment of the CMHS Project
Bulletin details some exciting news: Two
building projects are nearing completion.
The new Cancer Center is a beautiful addition
to our Ventura medical campus and will
soon provide patients with state-of-the-art
care in a peaceful, healing environment. In
Ojai, the PACU (Post Anesthesia Care Unit)
is in the final phase of construction and
will offer surgical patients a modern area
to recover. We've detailed both of these
projects in this bulletin, as well as provided
you with an update on construction of the
new hospital.

As one could imagine, a construction
project of this magnitude is a massive
undertaking. Building the new hospital is
a four-pronged parallel process:We must
receive approval from the city; receive
approval from the state; secure financing,
and-fourth-ensure that all of the design
elements of the building and surrounding
areas come together.
For the past several years, we have
been diligently working with the city on
every aspect of the project. This included the
Environmental Impact Review, which was
recently finalized.With the full support of the
Ventura City Council, City Manager and staff,
we are currently moving through the final
approval process, which included a meeting
with the Design Review Committee in late
October. In mid-November, we will meet with
the Planning Commission for the finishing
steps of the Memorandum of Understanding
(street closures, land swaps, parking, etc.),
and then the project goes before City Council
in December for their final approval.
Concurrently, we have been working
with the State of California. Although we had
hoped to have final approval by now, this
process has been slightly delayed due to the
state's fiscal crisis (offices closing, furlough
days). Our project has moved from Sacramento
to the Los Angeles Office of Statewide
Health Planning and Development (OSHPD)
and we are now working towards approval in
February.
Regarding financing, we are looking at
both an FHA option or financing through Cal
Mortgage. While we continue to explore our
financing options, final loan approval cannot
take place until the project is sanctioned by
OSHPD.
In tandem, we continue to work with
the architects and the contractor to ensure
the design elements meet expectations and
that the project costs stay within budget.We
remain confident as project and construction
costs have come down as we've gotten
closer to approval.

The Post Anesthesia Care Unit (PACU)
is in the final stages with with contractors
currently completing “punch list” items
noted by the architects. Once those items
are completed, hospital officials will contact
the California Office of State Health Planning
and Development (OSHPD). The state
must review and inspect the area before
issuing a Certificate of Occupancy. Barring
any unforeseen delays, hospital officials
anticipate the PACU will be open by the end
of November. Once the PACU is functioning,
the much-needed parking lot paving of the
entire campus will occur between November
22 to 26, weather permitting.All hospital and
skilled nursing facilities will be open during
this project.

As workers continue the finishing
touches on both the exterior and interior
of the building, a major component to
completing the Cancer Center took place
in October. One of two accelerators was
installed in the radiation vault. Physicists
were then brought in to test and calibrate
this incredibly important piece of machinery.
Following that, they turned the machine off
and are leaving it idle for up to five weeks.
If the equipment remains calibrated and
passes final testing once they turn it back
on in early November, it will receive state
approval for patient use.
In October, the exterior scaffolding was
removed and painting began. Additionally,
all of the glass features and windows –
which took nearly two months to install
– were completed. Part of the building's
design includes two large, glass-enclosed
linear galleries that are visible from Loma
Vista Road and Joanne Street, as well as the
center's parking lot. Hospital officials have
partnered with the city's public art program
to fill these spaces with artwork produced
by local artists. Additionally, on the corner
of Loma Vista and Brent Street the exterior
will be highlighted by a serpentine accent
garden that will feature palm trees and a
1950s flavor.
Tradesmen and women also completed
the exterior's roughly 140-foot covered
walkway, irrigation system, a majority of the
perimeter's low-level landscaping, the reflecting
pond and sidewalks. The architects
note that the sidewalk paving is from days
gone by and will feature sparkling quartz
accents.
Craftsmen are also putting the final
touches on the large lobby area, which
will be highlighted by a two-story terrazzo
staircase that is hung by cables – giving the
impression that it is floating in the air. The
staircase wraps around a central tile mosaic
mural nearly 18 feet tall serving as an
amazing focal point in the lobby.
The building designers note that the
use of colors and materials in the Cancer
Center are nature-based to provide a calm,
healing environment. As an example, the
elevators have bamboo-textured walls. The
architects also focused on making the area
as open and airy as possible, filled with
natural light.
This remarkable addition to the CMH
grounds has remained on time and on
budget. Excluding any unforeseen delays,
the Cancer Center is scheduled to open in
mid-November.


Gary K. Wilde, President & CEO
Community Memorial Health System
|